- 1、本文档共14页,可阅读全部内容。
- 2、有哪些信誉好的足球投注网站(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
- 3、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 4、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
查看更多
隧洞施工安全手册(英文对照)
一、一般规定:
1.1安全教育交底制度Safety Training and Disclosure System
针对洞内作业特点,施工前要对从事管理和生产的施工人员进行全面的安全教育,重点针对现场人员、班组长和从事特殊作业的操作人员和新职工。
Based on the characteristics of works inside tunnel, all managers and workers, especially site personnel, team leaders, the operators in special operations and new workers shall be trained comprehensively in safety before construction.
隧洞开挖开始以前,召开一次安全会议,对员工进行隧洞施工安全知识和具体危害的教育,这对以前有没有隧洞或较少经验的工人尤为重要。
Before the excavation of the tunnel, one safety conference shall be held so that safety education on the knowledge of tunnel construction safety and detailed hazard shall be carried out among construction personnel. This is very important, especially for the workers without or with little experience in the tunnel construction.
隧洞开挖过程中,每一个工序施工前,必须逐级向作业人员进行安全技术交底,交底人和被交底人应在交底书上签字,同时并定员检查、跟踪隧洞施工,及时反馈信息。
During the tunnel excavation, the clarification on safety and technology shall be made on all levels of staff before each working procedure starts. The technical informer and the technical informee shall sign on the clarification book, which shall be checked by the assigned worker for tracking the tunnel construction and feeding back the information.
1.2安全出入洞制度Going In Out of Tunnel Safety System
未经允许,非施工人员不得入内。
The non-construction personnel shall be not permitted to enter into the tunnel.
在洞口增设红绿警示灯,绿灯时表示正常工作状态,可进入;红灯时表示非正常状态或紧急处理状态,不可进入。
The red green caution light shall be installed at the tunnel portal. The green caution light means the normal work condition, so the construction personnel can go into the tunnel; The red caution light means the abnormal works condition or the emergency, so the constuction personnel can not go into the tunnel.
施工进洞人员实行翻牌制:在洞口挂一块板,每个进洞的工人将其名字下的“out”一面翻过去,改成“in”的一面。出来是再反过来改成“out”的一面。
The card-turnning system shall be observed by the construction personnels. One board with the name of all the construction personnels shall be set up in the tunnel portal, when the construction personnel goes into the tunnel, he or she shal
文档评论(0)