模板工程量计算(国外英文资料)
模板工程量计算(国外英文资料)
The calculation of template engineering
The types of basic components
It is divided into independent foundation, cup foundation and manchu foundation.
Strip foundation (no girder bar foundation, girder bar foundation), box form foundation
The calculation of basic templates
S = concrete and template contact area
The area of contact area of S = concrete and the template is equal to the base set length of the length by the height of the set
Solution
1. The analysis
It can be seen that this foundation is based on the beam type, which is the base of the base plate (thick 200mm) and the two sides of the beam (high 300mm). Therefore, the area of the contact area of concrete and the template should be calculated: the area of both sides of the base plate and the area of the beam.
Calculate the amount of work
Exterior wall:
Base plate S = (3.6 x 2 + 0.6 * 2) * 2 times 0.2 + (4.8 + 0.6 * 2) * 2 times 0.2 + (3.6-0.6 times 2) * 4 times 0.2 + (4.8-0.6 times 2) * 2 times 2 times 0.2 = 9.12 m?
The base beam S = (3.6 x 2 + 0.2 times 2) times 2 times 0.3 + (4.8 + 0.2 times 2) times 2 times 0.3 + (3.6-0.2 times 2) times 4 times 0.3 + (4.8-0.2 times 2) * 2 times 2 times 0.3 = 14.16 m, right?
Under the interior wall
Base board S = (4.8-0.6 x 2) times 2 times 0.2 = 1.44 m?
Base beam S = (4.8-0.2 times 2) * 2 times 0.3 = 2.64 m?
Basic template engineering = 9.12 + 14.16 + 1.44 + 2.64 = 27.36 m?
Were going to subtract the area of the inner wall in L
24 times 0.2 times 2 minus 1.2 times 0.2 times 2 is equal to 9.12 m2
24 times 0.3 times 2 minus 0.4 times 0.3 times 2 is 14.16 m2
The lateral column and the inner column
The column height of the beam board shall be calculated from the upper surface of the cylinder or floor to the top floor
The construction column template is calculated
A letter of S = (d1 + 0.12) * 2 * h
L, S = (d1 + 0.06) + (d2 + 0.06) + (0.06 by 2)
S = [d1 + 0.12] + (0.06 x 4)] * h cross S = 0.06 times 2 times 4 times h
Now cast concrete beam template
The typ