南方电网配网工程52-PWZDH-03配网架空线路开关配电自动化终端安装作业指导书-2012-要点
第8部分:配网工程
配网架空线路开关配电自动化终端安装作业指导书
编码:PWZDH-03
中国南方电网有限责任公司电网建设施工作业指导书 第 8 部分:配网工程
PWZDH-03配网架空线路开关配电自动化终端安装作业指导书
PAGE 434
PAGE 435
目次
1适用范围······················································································································································401
2编写依据······················································································································································401
3作业流程图···················································································································································401
4安全风险辨析与预控···································································································································402
5作业准备························································································································································13
6作业方法··························································································································································6
7质量控制措施及检验标准·······························································································································9
1适用范围
1.1电压等级
35kV及以下配网工程。
1.2电气类别架空线路柱上开关配电自动化终端安装。
2编写依据
表2编写依据
序号引用资料名称
1GB50171—1992《电气装置安装工程盘、柜及二次回路结线施工及验收规范》
2DL/T5161.1—2002《电气装置安装工程质量检验及评定规程第1部分:通则》
DL/T5161.8—2002《电气装置安装工程质量检验及评定规程第8部分:盘、柜及二次回路结线施工质量检验》
3Q/CSG10017.2—2007《110kV~500kV送变电工程质量检验及评定标准第2部分:变电电气安装工程》4Q/CSG11105—2008《南方电网工程施工工艺控制规范》5《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》
3作业流程图
图3作业流程图
4安全风险辨析与预控
4.1配网架空线路开关配电自动化终端安装作业前,施工项目部根据该项目作业任务、施工条件,参
照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的
风险分析表。
4.2按《指南》中与配网架空线路开关配电自动化终端安装作业相关联的《电网建设安全施工作业票》
(编码:PWZDH-03-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
序号危害名称风险种