南开大学 13春学期《工程施工》在线作业(国外英文资料)
南开大学 13春学期《工程施工》在线作业(国外英文资料)
13 spring semester project construction online homework
1. known P work has a tight work after G, G the latest finish time is fourteenth days and the duration of 3 days, the total float for the first P 2 days for sixth days, the duration is l days, P work for free float (days)
A. 1
B. 2
C. 3
D. 4
The correct answer: B Full Score: 2 points: 2
2. in the network planning, the total time of H work for 3 days, a total of three H J, K, tight L, J the earliest start time and latest start time is twenty-first days and twenty-second days, the earliest completion time of job K and latest finish time was twenty-third and twenty-fifth days L the earliest start time and latest start time were twenty-first days and twenty-third days, is the work of H (day) for free float
A. 1
B. 2
C. 3
D. 4
The correct answer: B Full Score: 2 points: 2
3. for the network of double code time scales drawn by the computation period, the following statement is incorrect
A. in addition to the network starting point, each nodes timescale is the earliest completion time of a job
B. in addition to the network endpoint, each nodes timescale is the earliest start time of a job
C. the total time difference is not zero, and the horizontal projection length of the arrow on the time axis is not equal to the duration of the work
D. wave arrow points at the node not just an arrow node
The correct answer: C Full Score: 2 points: 2
4. the strength of the lower member concrete and the strength of the lower member concrete shall be reduced to the design strength by means of the precast precast concrete pile
A. 20%
B. 30%
C. 40%
D. 50%
The correct answer: B Full Score: 2 points: 2
5. the construction of pre tensioned prestressed concrete. When the prestressed steel bar is relaxed, the strength of concrete should not be less than the design intensity grade
A. 75%
B. 80%
C. 85%
D. 100%
The correct answer: A Full Score: 2 points: 2
6. when the formwork and the support of the cast-in-place fl
您可能关注的文档
- 初二数学上册知识点总结(国外英文资料).doc
- 初二数学上册第一章 知识点(国外英文资料).doc
- 初二数学知识点(国外英文资料).doc
- 初二物理学习方法(国外英文资料).doc
- 初二物理重点记录(国外英文资料).doc
- 初党思想汇报(国外英文资料).doc
- 初二语文期中试卷(国外英文资料).doc
- 判断 首字母汇 高级工(国外英文资料).doc
- 判定两个三角形全等的基本思路见下表(国外英文资料).doc
- 利用视觉力量 激发自我潜能(国外英文资料).doc
- 养成卫生好习惯 (教学设计)-2024-2025学年沪教版(五四学制)小学体育与健康一年级全一册.docx
- 整理书包 (教学设计)-2024-2025学年山东科学技术版(2023)小学综合实践活动一年级上册.docx
- 好玩的手影游戏 (教学设计)-2024-2025学年山东科学技术版(2023)小学综合实践活动一年级上册.docx
- 纸飞机 (教学设计)-2024-2025学年山东科学技术版(2023)小学综合实践活动一年级上册.docx
- Unit1《A new start》(教学设计)-2024-2025学年外研版(2024)初中英语七年级上册(3课时).docx
- 学习用品常整理 (教学设计)-2024-2025学年山东科学技术版(2023)小学综合实践活动一年级上册.docx
- 我的身体我了解 (教学设计)-2024-2025学年沪教版(五四学制)小学体育与健康一年级全一册.docx
- 七巧板(教学设计)-2024-2025学年苏科版(2023)小学劳动技术一年级上册.docx
- 小风车(教学设计)-2024-2025学年山东科学技术版(2023)小学综合实践活动一年级上册.docx
- 小鸟的旅行 (教学设计)-2024-2025学年湘美版(2024)小学美术一年级上册.docx
文档评论(0)