Key points of safety supervision in winter construction
I. Basic provisions:
1, during the winter construction, we should establish contact with the meteorological department, timely grasp the snow situation, wind and other forecasts, understand the abrupt change weather situation, and take corresponding preventive measures in a timely manner.
2, in the construction process of engineering project site changes or have larger design changes, should be adjusted in time to supplement construction program and safety technical measures.
3, heavy snow, fog, dust storms, wind 6 (including) more than the bad weather, shall not be hoisted, drilled, high-altitude and other outdoor operations.
4, the snow after the operation, in addition to the snow outside, should also be safety device for inspection of special equipment, cable without damage, wire joints without damage, the overhead line is no exception, whether there is a hole in the snow.
5, the project management department should be fire prevention, antifreeze, anti-skid, gas poisoning, anti spring melt collapse to develop special safety management measures and systems, special safety disclosure and education.
6, before the winter, with facilities take weatherization measures.
7, during the spring thaw period must be carried out before the start of the engineering geological investigation, determine the freezing depth and soil thaw categories, check on pit, slope, found the danger signs and timely treatment.
Two. Prepare the work before winter application
1, winter construction project safety management organization, to the Post search people.
2, key staff quarters, on-site temporary power consumption, construction, fire protection, anti freezing, anti-skid, gas poisoning prevention and operation on the side of the high side protection measures. Where there is a potential safety hazard and where the safety precautions are not in place, measures shall be taken and fixed time rectification shall be carri