FIDIC红皮书中承包商遭受延误和(或)招致费用增加的处理

Contractor Suffers Delay and/or Incurs CostClauseconditionTimeCostProfit1.9Delayed Drawings and InstructionsIf the Contractor suffers delay and/or incurs Cost as a result of a failure of the Engineer to issue the notified drawing and instruction within a time which is reasonable and specified in the notice with supporting details…√√√2.1Right of Access to the SiteThe Engineer shall give the Contractor right of access to, and possession of, all part of the Site within the time (or times) stated in the Appendix to Tender.If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right of possession within such time…√√√4.7Setting OutThe Contractor shall set out the Works in relation to original points, lines and levels of reference specified in the Contract or notified by the Engineer.The Employer shall be responsible for any error in these specified or notified items of reference.If the Contractor suffers delay and/or incurs Cost from executing work which was necessitated by an error in these items of reference , and an experienced contractor could not reasonably have discovered such error and avoided this delay and/or Cost…√√√4.12Unforeseeable Physical ConditionsIn this Sub-Clause, “physical conditions” means natural physical conditions and man-made and other physical obstructions and pollutants, which the Contractor encounters at the Site when executing the Works, including sub-surface and hydrological conditions but excluding climatic conditions.If the Contractor encounters adverse physical conditions which he considers to have been Unforeseeable, the Contractor shall give notice to the Engineer as soon as practicable.If and to the extent that the Contractor encounters physical conditions which are Unforeseeable, give such a notice, and suffers delay and/or incurs Cost due to these conditions…√√4.24FossilsAll fossils, coins, articles of value or antiquity, and structures and other remains items of geological or arch

文档评论(0)

xcs88858 + 关注
实名认证
内容提供者

该用户很懒,什么也没介绍

版权声明书
用户编号:8130065136000003

1亿VIP精品文档

相关文档