VIETNAM OIL AND GAS CORPORATION (PETRO-VIETNAM)
DUNG QUAT REFINERY (DQR) PROJECT
METHOD STATEMENT FOR
ROTATION MACHINE
Document No.:8474L-800-17059-6800-MS012-Rev.
Document Class : Z
REVIEW BY: TPC REVIEW BY PMC/DQR CODE 1 Revise and Resubmit CODE 1 Revise and Resubmit CODE 2 Review With Comments Work May Proceed/Revise Resubmit CODE 2 Review with comments Work May Proceed/Revise Resubmit CODE 3 Review Without Comment Work May Proceed CODE 3 Review Without Comment Work May Proceed STAMP STAMP SIGNATURE SIGNATURE NAME NAME DATE DATE REVIEW STATUS A Nov 8,2007 For Review REV. DATE STATUS ORIGINATOR (NAME VISA) CHECKER (NAME VISA) APPROVER (NAME VISA) DOCUMENT REVISIONS
CONTENT
GENERAL
REFERENCE DOCUMENTS
PREPARATION WORK
INSTALLATION FOR ROTATION MACHINE (COMPRESSOR)
INSTALLATION OF PUMPOTHER ORTARY EQUIPMENT
HSE
Organization Chart
Job Safety Analysis
Attachment.1. Organization Chart
Attachment.2. JOB SAFETY ANALYSIS
1.General
This procedure is provided to guide the field installation work for rotation machine in ME1 in Dung Quat refinery project. the main rotary machinery includes pumps, blowers, boilers, compressors, Agitators,and other machines.
The procedure covers the general requirement for the installation of compressor and other rotary machinery equipment. In general, the rotating equipment installation shall be in accordance with the relative specification. Any other special requirements for the installation specified in the manufacture instructions shall be strictly complied.
2.reference documents
1. 8474L-000-pp-208 Project Equipment List
2. 8474L-000-PP-809 Project Procedure-Site Quality Plan
3. Drawing issued by TPC and or rotation machine specification offered by manufacture
3. Preparation Work
3.1 Preparation work of technical document
3.1.1 Equipment assembly drawings and installation drawings of the whole package, drawings for important components,
您可能关注的文档
- 第三:仪态礼仪.ppt
- VR实例教程2.ppt
- 商道AdWords分享:这些.doc
- 分子生物学Chapter4.ppt
- 软件开发技术复习(20101221duwei).doc
- 浮力相关练习.doc
- 1.2三大自然区的内部差异--新.ppt
- 2012年北京市中考数学二模代数几何综合题及答案.doc
- 法律风险控制表.doc
- 课件、报告用ppt模板2.ppt
- 《GB/T 32151.42-2024温室气体排放核算与报告要求 第42部分:铜冶炼企业》.pdf
- GB/T 32151.42-2024温室气体排放核算与报告要求 第42部分:铜冶炼企业.pdf
- GB/T 38048.6-2024表面清洁器具 第6部分:家用和类似用途湿式硬地面清洁器具 性能测试方法.pdf
- 中国国家标准 GB/T 38048.6-2024表面清洁器具 第6部分:家用和类似用途湿式硬地面清洁器具 性能测试方法.pdf
- 《GB/T 38048.6-2024表面清洁器具 第6部分:家用和类似用途湿式硬地面清洁器具 性能测试方法》.pdf
- 《GB/T 18238.2-2024网络安全技术 杂凑函数 第2部分:采用分组密码的杂凑函数》.pdf
- GB/T 18238.2-2024网络安全技术 杂凑函数 第2部分:采用分组密码的杂凑函数.pdf
- 《GB/T 17215.686-2024电测量数据交换 DLMS/COSEM组件 第86部分:社区网络高速PLCISO/IEC 12139-1配置》.pdf
- GB/T 13542.4-2024电气绝缘用薄膜 第4部分:聚酯薄膜.pdf
- 《GB/T 13542.4-2024电气绝缘用薄膜 第4部分:聚酯薄膜》.pdf
文档评论(0)