管井降水施工方案
The construction scheme of tube well dewatering
柬埔寨安达都会广场项目
VCLP PROJECT CAMBODIA
编制单位:Sinoma HanDan Construction Co.,Ltd
编 制:
compiled:__________________
审 批:
Verified: __________________
批 准:
Approved: __________________
日 期:
Date : __________________
安达广场基坑降水施工方案
Construction Scheme for Foundation Pit Drawdown of VATTANAC Park
一、降水设计方案
I. Drawdown design scheme
1.1、设计参数
1.1. Design data
本工程降水井采用直径300mm波纹管滤管,管井共20根井深22米,井口外露500mm。
300mm corrugated filter pipe is adopted as the drawdown well and there are total 20 wells of 22m deep each. The wellhead exposes by 500mm.
1.2、降水井平面布置
1.2. Layout of drawdown well
降水井布置详见降水管井平面布置图。
The arrangement of drawdown well is shown on the layout of drawdown well.
二、施工准备
II. Construction preparation
2.1、测量放线
2.1. Surveying and setting out
测量放线依据现场测量控制点,标高采用水准仪,并根据井点布置图采用全站仪放线定位。放线经复核后报管理公司确认方可进行施工。
The surveying and setting out shall be based on the field survey control points and optical level shall be used for measuring the elevation. In addition, the total station instrument shall be used for the setting out and positioning according to the layout of well points. Setting out shall be performed after re-recheck and being reported to the management company for confirmation.
2.2、施工用电、用水配置
2.2 Electricity and water for construction
1、施工用电直接从配电房接入,50kVA能完全满足降水用电负荷。
1. The electricity for construction shall be directly connected from the switchgear room, and 50kVA can fully meet the drawdown load requirements.
2、依据用水设备和施工经验,需用水量10m3/h直径50mm管,就能满足施工用水。
2. Depending on the water equipment and based on the construction experience, the pipe of diameter 50mm with a water flow rate of 10m3/h can meet the construction requirements.
2.3、打井机械及井点设备
2.3. Well drilling rig and well point equipment
打井机械可根据工期要求变更。井点设备是由井点管、连接管、排水主管及抽水设备等组成。具体如下:
The well drilling rig may very according to the schedule requirement. The well point equipmen
您可能关注的文档
最近下载
- 沪教版七年级数学上学期考试满分全攻略第10章分式【单元提升卷】(沪教版)(原卷版+解析).docx VIP
- 学生心存感恩主题国旗下讲话稿.docx VIP
- 《妇幼保健学》课件——第十二章 围绝经期保健.pptx VIP
- 2024年全国职业院校技能大赛中职组(舞蹈表演赛项)考试题库(含答案)_已识别.pdf VIP
- 译林四上 Project1 教学课件.ppt VIP
- 乳腺癌的护理常规课件.pptx
- 2023年驾培相关项目运行指导方案.pdf VIP
- 个案工作 第八章-儿童辅导.pptx VIP
- 2024年山西航空产业集团有限公司人员招聘考试题库及答案解析.docx
- 运动解剖学(李世昌)第4章 消化系统.ppt VIP
文档评论(0)